Fiscal Year 2013-2015 Special Budget Meeting
Informational ReportFiled under council matter 12-0351
Subject: Fiscal Year 2013-2015 Special Budget Meeting From: City Administrator's Office Recommendation: Receive A Presentation And Hold Discussion On The Mayor's Proposed Budget For Fiscal Year 2013-2015
Extracted text
HONORABLE MAYOR AND CITY COUNCIL
Subject: Proposed FY 13-15 Proposed Policy Budget
Date: June?, 2013
Page 13
Equi pment. Material and Supplies
Vehicles, lawn mowers, maintenance supplies
$1,390,244
Initial Personnel and O&M Costs:
$4,513,468
3) How much would it cost to maintain all the new parks around Lake Merritt?
As noted in the previous question, since 2008, Public Works has had a reduction in park
maintenance staff due to budget cuts. The gardening staff responsible for maintaining the Lake
Merritt area along with all other parks city-wide was reduced more than 50% over the last 5
years. The staff reduction impacted the ability to maintain the park in an acceptable manner
given the increased areas fi-om Measure DD projects and the growing use of Oakland parks.
Lavms are mowed less frequently, litter abatement response is less frequent, and general routine
landscape maintenance (pruning, edging, fertilizing) has diminished.
Over the last few years, several Measure DD projects have been completed along Lakeshore
Avenue and east of the Pergola, both of which have added extensive landscaped and hardscaped
areas. Currently the 12* street project is nearing completion, adding a new pedestrian and a
roadway bridge, new parkland that includes restrooms, several amphitheaters, outlook area, three
vegetated storm water features (basins and swales), new pathways, seat walls, lawn areas, and
new landscaping in several traffic islands. There are five (5) additional acres that need to be
maintained. The 3-year Plant Establishment Period for the 12^" Street project will cover the
maintenance of the new landscaping but does not cover maintenance of the hardscape, graffiti or
litter related issues.
Moreover, in the next year additional new projects will begin construction; future fimding will
need to be identified for these projects, 10 Street with new landscaping and pathways. Snow
Park which expands the current park, and the Sailboat House project with decreases the size of
the parking lot and creates new shoreline and landscaped areas. These projects add about 3 new
acres of landscaped assets and new hardscape infrastructure that will need to be maintained.
Financials
Below, you will find a chart that shows a comparison of the current service level, versus
proposed service level A &B. The second chart lists the cost for providing a comprehensive
maintenance program for Lake Merritt (Service Level A). The third chart identifies the minimal
cost to improve current maintenance services at Lake Merritt (Service Level B).
Activity
Current Service Level
Service Level A
Service Level B
Mowing
Every 3 weeks
Weekly
Every 12-14 Days
Edging and Pruning Every 4-6 Weeks
Bi-weekly
Monthly