Proposed CIP
Page 7
Funded, Non‐Discretionary Projects
These projects are those that are either mandated upon the City by court order or other legislation
(e.g., sanitary sewer capital improvements; construction of curb ramps) or where the funding
source limits the type of project to be funded. The majority of projects recommended for
adoption in the attached CIP fall into this category. A total of $87.8 million is recommended for
investment in these projects. A summary of these projects:
Buildings and Facilities, 7 projects, $1.4 million
Sewers - 12 projects, $29.1 million
Streets, Sidewalks - 10 projects, $19.6 million
Traffic Improvements - 5 projects, 4.5 million
Garage Improvements – 3 projects, $33.2 million (subject to State Approval of
Redevelopment disposition)
Funded, Discretionary Projects
These are projects for which funding is available that are not mandated or are funded through
sources such as General Purpose Fund or other funds that do not have limits on their
expenditures.
Mandated Projects
These are projects with no available source of funding but which are mandated by federal or state
law. Staff carefully analyzed all projects submitted for inclusion in this category and sought
confirmation of any relevant legislation. A total of 4 projects representing a needed investment
of $1.8 million were identified. Examples of these projects include boiler replacement and
elevator upgrades. While no funding source has been identified, these projects are presented for
consideration should funding become available.
Major Unmet Requests
This category includes projects that replace or renovate assets which are either structurally or
functionally obsolete or have deferred maintenance issues that negatively value the asset but for
which no funding is available. This category includes:
Major projects that improve or replace key assets. Examples include:
o Emergency services facilities such as the Police Administration Building and
some fire stations that do not meet the criteria of essential service facilities (fully
operational after an earthquake or similar disaster) or have significant deferred
maintenance items that impact their operational status.
o Street Resurfacing and sidewalk repairs, to address the backlog throughout the
City in assets that must be maintained.